Wednesday, September 19, 2012

Gardenqub progress update

Hi Everyone,
The Gardenqub is taking shape!
What have we achieved?


The foundations are set out and dug.
Note the offset string lines locating the centre of the footings.

 A close up of the sting lines and the dug foundation. Foundations are 60 x 60 x 60cm

Concrete is poured and a starter pipe set in the center of the Gardenqub foot.
All foundation pipes are set to the same height.

  Here you see all the foundations set.

Foundations are backfilled to a level just below the top of the foundation pipes. The rest will be filled with stones so as to allow water to drain away from the Gardenqub feet once they are set.

Power conduit is laid to one of the Gardenqub corners.

This is the completion of the foundation work for the Gardenqub installation.